PERFORMANCE CONSIDERATIONS

Lighting

 

Although a small percentage of total energy use, lighting is an important part of most EPC contracts. 

 

Firstly, it is relatively easy and cost effective to implement lighting energy upgrades, as technologies are improving all the time (new lamps, fittings and controls) and many lighting installations are very inefficient.  The huge improvements reported from USA and Europe are not generally available in Australia as we have lower lighting levels to begin with, hence less equipment to upgrade, however substantial savings (typically 20 –40% and up to 80% in some cases) can be found.

 

Secondly, lighting is a relatively simple technology to understand (compared with HVAC for instance).  Upgrading the lighting sends a very obvious message to staff, patients and the public that the facility is serious about reducing its energy use.

 

Thirdly, because lighting consumes electricity, not gas, it has a disproportionate impact on greenhouse emissions . Coal fired electricity emits around 5 times the greenhouse gas per unit of energy than natural gas, so saving a unit of energy in lighting has 5 times the impact of reducing a unit of gas used in  HVAC or water heating for example.

 

General techniques applied in the lighting upgrade of these facilities included:

 

 

 

Table 2 Comparison of lamp types

(for approximate equivalent light output)

 

Tungsten

CFL

40

9

75

15/18*

100

20/25*

 

* depends on style of lamp

 

  1. Poor quality equipment, either inadvertently or as a result of taking the cheapest price, and

  2. Selecting the wrong technology.

 

A simple example of the latter has been occupancy detectors which have a mixed, but largely undeserved reputation for being unreliable.  Broadly there are two types, infra-red and ultra-sonic; using the wrong one can result in unwanted operation or worse, no operation at all.  Using a lighting controls specialist avoids these problems.

 

Example:  a lighting upgrade at Parramatta Linen Service comprised de-lamping in areas with excess lighting, new control equipment, new reflectors and dimming.  Prior to the work the annual electricity used by the lighting system was estimated at 359,079 KWh by measuring for 2 weeks and extrapolating over a full year.  This is s standard technique.  When the modifications were completed the electricity consumption was similarly measured over a period of 2 weeks, resulting in estimated savings of 93,365 KWh or 26%.

 

Heating Ventilating And Air Conditioning

 

Heating, Ventilating and Air Conditioning, commonly referred to as HVAC, is the major energy user in most commercial, institutional and industrial facilities.  It usually provides the greatest opportunity for energy savings as almost all HVAC installations in Australia rank poor to fair when they are assessed for efficiency, greenhouse impact and overall effectiveness.  Energy reductions of 10-20% are common under an EPC, with reduced maintenance, increased effectiveness and lower emissions also contributing to the benefits achieved by a sensible upgrade.

 

HVAC improvements include Boilers, (for space heating and domestic hot water), and automatic control systems, as well as the more common features such as pumps, fans, chillers and cooling towers.

 

EPC’s are particularly effective when applied to HVAC systems, as they can also be used to renew old and out-of-date equipment, replacing it with newer plant and systems which not only perform more effectively but last longer as well.  This means that a major capital cost item, often difficult to fund (such as the replacement of aging plant), can be carried out as part of an EPC, paid for from the total operational savings from the project.

 

For this project, the HVAC associated actions accounted for 95% of total energy savings.  The major strategies implemented were:

 

 

 

 

 

Power Factor Correction

 

Power factor is a measure of the efficiency with which electricity is used on a site.  A Power Factor of 1 is the ideal, most commercial businesses run somewhere between 0.7 and 0.95.  Poer Factor is usually improved by installing banks of capacitors at the main electrical switchboards.

 

Power factor correction is not of itself an energy saving project, however, it is a significant energy cost saver where there is a charge (or penalty) for low power factor.  In these cases the closer the power factor is to unity (1) the lower the total electricity charge.  This technique can also increase the capacity of existing electrical distribution systems so it may sometimes be a way of accommodating increased electrical load without the capital expense of additional wiring and switchgear.

 

For this contract power factor correction units were installed to increase the Power Factor at sites such as Bloomfield and Blayney Hospitals, from 0.85 to 0.98. 

 

Water Saving Devices

 

Water is often overlooked as a cost saving opportunity, largely due to Australia’s long history of free water and lack of awareness of the significant costs involved in water and sewerage charges. There is often little understanding of the ways in which these charges can be reduced. Strategies for reducing water costs include:

 

Reducing total water use by:

 Reducing waste charges by:

 

Recommended water flow rates

 

Fixture

Recommended Flow - litre/min.

Typical Uncontrolled Flow - litre/min.

Basin tap

6

15

Kitchen sink

12

15

Shower

8-12

15-30

 

For the  AHS sites, an inspection revealed that tap and shower fittings at the hospitals were inefficient, and inlet and outlet seals on toilet cisterns were in poor condition and in need of repair. As a result, water was unnecessarily wasted. Water conservation measures implemented were: