DESIGN ISSUES
An advertisement was placed in the media calling for Expressions of Interest (EOIs) from contractors, to which seven replies were received. After a detailed evaluation process, three were selected to conduct a walk-through study of the sites and submit preliminary technical and financial proposals. These proposals underwent an independent evaluation to select a contractor to prepare a Detailed Facility Study (DFS), This study outlined more accurate details of the technical projects, and full financial and contractual matters.
NSW Treasury has set up a fund specifically to fund EPCs [NP1]in NSW Government agencies and this was used to finance the EPC. Other sources of finance are available for non-NSW Government agencies.
The contract work commenced in September 1999 and was completed in April 2000. The EPC contract period including guaranties concludes in April 2005. The first quarterly monitoring and verification meeting was held in August 2000 at which progress was assessed against the targets. The results were satisfactory given the complexity of the projects and changes in the operating conditions; some minor adjustments have been made to account for these changes. .
EPC contracts are usually assessed using an Internal Rate of Return (IRR) as the measure of financial viability. Internal Rate Of Return is effectively the interest rate earned, over a period of time, on an investment taking into account issues such as:
¨ Capital cost
¨ Cost of financing
¨ Cost savings
¨ Expenses such as maintenance
¨ Inflation
Because EPCs are long-term contracts, IRR is preferred because it:
¨ Takes account of the time value of money
¨ Allows variable cash flows as different projects are implemented in different years
¨ Provides a simple number (an interest rate) which can be easily compared to other investment options
The initial IRR calculation was based on:
Initial Capital: $2,100,000
Initial savings: $530,126
Term : 15 years
Discount rate: 7%
Inflation rate: 3%
The financial performance of the project was then estimated to be:
IRR: 27%
NPV of Savings: $5,769,373
NPV Net of Investment: $3,670,376
Payback Period (years): 3.96
Between the time the original proposal was developed and the DFS was finished there were a number of changes to the scope, as is often the case. As a result the final estimate of financial performance was:
IRR: 20%
NPV of Savings: $5,121,634
NPV Net of Investment: $2,636,804
Payback Period (years): 5.68
While this is not as attractive as first suggested, it is still an excellent investment by any standards and the AHS was happy to commit to implementing it.
Another important benefit of EPC is the openness in which the risks associated with any project are disclosed and negotiated. This is in stark contrast to the more normal adversarial contracts common in the building and services industries, where the contractor tries to ensure all the risks are carried by the client while not actually telling them what they are.
For the Mid Western Area Health Service (MWAHS) EPC a full risk disclosure was made and decisions taken to share the risks depending on who was the most likely party to be able to control it. As a result the following table was drawn up and included in the contract.
Table 1 Contract Risk Profile
|
|
Risk |
Borne by |
Comments |
|
1 |
ownership of existing assets |
MWAHS |
all existing assets remain with the MWAHS |
|
2 |
ownership of new assets |
MWAHS |
new assets are the property of the MWAHS once paid for |
|
3 |
Inflation |
Contractor |
all prices quoted are fixed |
|
4 |
insurance of new work |
Contractor |
|
|
5 |
stamp duty/taxation |
Contractor |
included in cost of project |
|
6 |
Finance |
MWAHS |
MWAHS through NSW Health will access the funding set up by NSW Treasury for EPC’s |
|
7 |
building approvals |
Contractor |
|
|
8 |
performance/savings being achieved |
Contractor |
contractor will reimburse MWAHS should savings not meet guaranteed levels |
|
9 |
altered systems meeting Australian standards and NSW Health guidelines |
Contractor |
|
|
10 |
Maintenance of new and old equipment and operating cost management |
MWAHS & Contractor |
items included in maintenance contract to be maintained by contractor at fixed annual cost |
|
11 |
monitoring and verification of savings |
Contractor |
contractor to submit quarterly and annual reports and reconciliations |
|
12 |
Determination and movement of baselines |
Contractor & MWAHS |
framework exists however both sides must be in agreement |
|
13 |
repair of new equipment |
Contractor |
Contractor responsible for 5 year term of maintenance contract and guarantee period |
|
14 |
fuel price risk |
MWAHS |
Conservative estimates used during analysis |
|
15 |
ownership of drawings designs and specifications |
Contractor & MWAHS |
MWAHS to own all drawings and documentation once fees have been paid. IP in contractors software to remain property of contractor |